Building Committee Update
Thanks to the combined efforts of our Building Committee and design team - including Lacey-Convertino Architects, Stephens Engineering, and the Store Development Services at United Natural Foods - a thorough set of design and construction drawings was completed in mid-July.
We proceeded into the contractor bidding process immediately in late-July, and it culminated last week with the Building Committee's review of six bid submissions. We were pleased with the strong response during our bid period, and are grateful to all participating contractors for their interest in our project.
J. Luk Construction Company of Schenectady delivered the lowest bid proposal, at $443,900. Eric Paul and I met with owner John Luke Hodorowski earlier this week to discuss the details of the project, and we feel that he understands the mission of the TCFC, and our overall vision for the renovations of the Pioneer Market very well. The Building Committee confidently recommended J. Luk Construction to be selected by the Board, and their bid was unanimously accepted. We are eager to add John and his company to our team!
You will begin seeing the signs of progress in the Pioneer Market over the next few months.
We are currently reviewing bids from asbestos abatement contractors, and anticipate that full remediation of the Pioneer Market will be completed by the end of September. Once our financing is approved, we will begin the three-month general construction period, followed by another month of store setup and staff training. Then the TCFC will open its doors to the public!